J
JodyJ
I have a task with the task type of fixed work. 2 resources assigned, 10hrs
each, 81% units, MS Project calculates duration of 3.09 days. If I increase
the units on both resources to 100%, the duration recalculates to 2.5 days,
"work" doesn't change. This is as I expected.
If I increase the duration to 5 days the units on one resource changes to
36% but the other remains the same. Why?
If I decrease the duration to 1 day, units on one resource changes to 125%
but units on the other resource changes to 0% and "work" changes to 10 hrs.
Why?
I thought with a "fixed work" task, "work" shouldn't change.
each, 81% units, MS Project calculates duration of 3.09 days. If I increase
the units on both resources to 100%, the duration recalculates to 2.5 days,
"work" doesn't change. This is as I expected.
If I increase the duration to 5 days the units on one resource changes to
36% but the other remains the same. Why?
If I decrease the duration to 1 day, units on one resource changes to 125%
but units on the other resource changes to 0% and "work" changes to 10 hrs.
Why?
I thought with a "fixed work" task, "work" shouldn't change.