D
DWeb
Hello! I am hoping someone can help me answer this question. My project
team enters hours worked twice monthly according to corporate time periods,
generally the for periods ending on the 15th or 30th/31st of each month.
I am trying to enter hours for each resource into the Resource Usage View to
reflect the total hours for a given period. Unfortunately, the summary sheet
I am working from has hours under 3/15, 3/31, etc., whereas when I adjust the
timescale in the Resource Usage view in Project, I get week BEGINNING dates
of 3/13, 3/27, etc.
Is there any way I can adjust the timescale in Project to reflect the way my
data is organized so that I can just enter it directly from my summary
spreadsheet without having to work with the the underlying day by day hours?
team enters hours worked twice monthly according to corporate time periods,
generally the for periods ending on the 15th or 30th/31st of each month.
I am trying to enter hours for each resource into the Resource Usage View to
reflect the total hours for a given period. Unfortunately, the summary sheet
I am working from has hours under 3/15, 3/31, etc., whereas when I adjust the
timescale in the Resource Usage view in Project, I get week BEGINNING dates
of 3/13, 3/27, etc.
Is there any way I can adjust the timescale in Project to reflect the way my
data is organized so that I can just enter it directly from my summary
spreadsheet without having to work with the the underlying day by day hours?