L
LG
I have several forms built. 1 is there the processor puts in their daily
schedule and time off production. Another is the supervisor enters daily
work and maybe more than 1 entry in a day. another form is a processor form
where they locate the work assigned and mark a complete date on it.
When i run the report for total amount of work time - time off to coincide
with the assignments I can't get the hours to update the table.
For ex. Supervisor enters assigned 100 on 6/12/09 and than another entry for
the same person 150 on 6/12/09. The processor than goes in on the form and
inputs their hours for today. On another form the go to the batch that was
assigned and put a complete date or leave it bland if they were not all
completed. i can't get the report to tally the hours on the same line as the
work assigned. Any suggestions?
schedule and time off production. Another is the supervisor enters daily
work and maybe more than 1 entry in a day. another form is a processor form
where they locate the work assigned and mark a complete date on it.
When i run the report for total amount of work time - time off to coincide
with the assignments I can't get the hours to update the table.
For ex. Supervisor enters assigned 100 on 6/12/09 and than another entry for
the same person 150 on 6/12/09. The processor than goes in on the form and
inputs their hours for today. On another form the go to the batch that was
assigned and put a complete date or leave it bland if they were not all
completed. i can't get the report to tally the hours on the same line as the
work assigned. Any suggestions?