Hello,
MS Project can lock only one column on the left hand side. By default it's
the ID column .
You can change the table definition: put the Task name as the first column:
- View / Tables / More tables /
- Select the table you want "entry" by default
- Modify
- Cut/paste the Name column
Hope this helps,
Gérard Ducouret