Freezing Data when resources are stripped out

B

Blueglass

Is there a way to maintain Start/Finish dates, Duration, % Complete, and
Constraint Type when stripping out Resources and setting Work equal to 0?
 
J

Jim Aksel

You can memorialize this data by copying it to spare text or date fields
prior to stripping out the data.

You could also set an artificial baseline... Tools/Tracking/Save Baseline
then select something like Baseline4. The data should be saved there,
although %complete would not be.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
J

Jim Aksel

Thank you for the feed back. Please keep let us know if you need additional
assistance.
--
Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 