K
Kim
Activity 1, duration 1day. Activity 2 FS relationship with Activity 1.
Standard calendar.
End date of Activity 1 - 9/1/09 @ 5:00pm
Start date of Activity 2 - 9/1/09 @ 5:00pm; finish as soon as possible
Project calendar - 8 hrs per day; default start 8am; default finish 5pm
Task calendar - 8 hrs per day; 8a-noon & 1p-5p
I expected to see Activity 2 start at 8am on 9/2/09. Why is Activity 2
starting at exactly the same time as the end of Activity 1.
Using MS Project 2003. Any advice is greatly appreciated! Thanks.
Standard calendar.
End date of Activity 1 - 9/1/09 @ 5:00pm
Start date of Activity 2 - 9/1/09 @ 5:00pm; finish as soon as possible
Project calendar - 8 hrs per day; default start 8am; default finish 5pm
Task calendar - 8 hrs per day; 8a-noon & 1p-5p
I expected to see Activity 2 start at 8am on 9/2/09. Why is Activity 2
starting at exactly the same time as the end of Activity 1.
Using MS Project 2003. Any advice is greatly appreciated! Thanks.