FS to SF predecessors

W

warnimont

Let's say we're discussing task 2.
i want to set task 2 start at the completion of task 1 and
finish at the start of task 3.
task 2 duration will change as task 1 and 3 move.
How is this done?????
 
W

warnimont

You're a god. I have been trying to figure this out for
years.
I gave..then found this forum and figured I'd try again.
It works!!!!!!!!!!!
 