B
bgane
I would like to use the calendar to specify part-time vs. full-time
employees, which works fine, unless you are using multiple resources on a
task. Two scenarios:
1. I have two resources...1 full-time and 1 part-time. I specify the
part-time by setting their working time from 8 to 12 in the calendar. I then
apply both the full-time resource and the part-time resource at 75% to a task
scheduled for 3 days. The Duration calculates to 3 days, which is incorrect.
2. I have two resources...1 full-time and 1 part-time. Both are listed in
the calendar as full-time. I then apply the full-time resource at 75% and
the part-time resource at 38% (gives me 3hr, which is the same as a part-time
set for 4hrs/day at 75%) to a task scheduled for 3 days. The Duration
calculates to 2.65 days, which is correct.
I want to use the first method because I want the calendar to do all the
work for me, but I cannot get it to calculate correctly. Please help.
employees, which works fine, unless you are using multiple resources on a
task. Two scenarios:
1. I have two resources...1 full-time and 1 part-time. I specify the
part-time by setting their working time from 8 to 12 in the calendar. I then
apply both the full-time resource and the part-time resource at 75% to a task
scheduled for 3 days. The Duration calculates to 3 days, which is incorrect.
2. I have two resources...1 full-time and 1 part-time. Both are listed in
the calendar as full-time. I then apply the full-time resource at 75% and
the part-time resource at 38% (gives me 3hr, which is the same as a part-time
set for 4hrs/day at 75%) to a task scheduled for 3 days. The Duration
calculates to 2.65 days, which is correct.
I want to use the first method because I want the calendar to do all the
work for me, but I cannot get it to calculate correctly. Please help.