Hello Tony,
Check the layout of the Gantt chart. Format > Layout and experiment
with the "Round bars to whole days" option. I assume the start and
end times are correct in the task sheet (left side)?
Also for your future reference, please do not post in all upper case.
It is very difficult to read and is generally considered to be
screaming.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"(e-mail address removed)"