Gantt Bars to go RED

S

schemr

hi,
i wud like to make my Project 2003 so that when a task has past its finish
time, the corresponding task bar in the gantt chart go RED color. how would i
do this? thanx in advance

schemr
 
J

Jan De Messemaeker

Hi,

A task cannot go past its finish time since as long as it runs it is not
finshed :)
It can however go beyond its originally planned finish time.
That one in turn can be saved into Baseline Finish (Tools, Tracking, Save
Baseline)
Now customize a flag field such that it goes to Yes when Finish>Baseline
Finish
Then add a bar to the bar stylmes which is red when that flag field is on.

And before all read

http://www.mvps.org/project/faqs.htm
Faq 31. Customizing Gantt Bars

HTH
 