Gantt Chart and Resource view

J

Joey

I have multiple sections of a project in the Gantt Chart view. I wanted to
be able to highlight tasks in this view and have them still be highlighted in
the Resource Usage View so I can tell which section the tasks came from. I
know the Gantt Chart and Resource Usage view use two different tables so does
anyone know how to do this?

Thanks, Joey
 
J

Jan De Messemaeker

Hi,

Highlighting can not be transferred to the Usage View, Sorry.
You can transfer a custom field such as Text7, Number5, etc... which can
help you sort, filter or group in the resource Usage View; if you're
interested I can post a macro doing that.

But highlighting, sorry, no.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

Joey

Thanks.

However I could not get that to work. I tried entering data in column text
1 in the Gantt Chart view but nothing shows up in the Resource Usage View.
 
J

Jan De Messemaeker

Hço,

Sorry for not making myself clear. You need VBA code to do that, that's what
I ment. It doesn't happen spontaneously. If you can implement a macro, I'll
send the code.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

Jan De Messemaeker

Hi,

Please.
This is the version for Project 2007, the older version can be found in FAQ
37 in
http://www.mvps.org/project/faqs.htm

Sub Task_CF_To_Resource_Usage()
Dim Reso As Resource
Dim Task_As As Assignment
Dim Reso_As As Assignment
Dim Job As Task

For Each Job In ActiveProject.Tasks
If Not Job Is Nothing Then
For Each Task_As In Job.Assignments
Task_As.Text1 = Job.Text1
Set Reso = ActiveProject.Resources(Task_As.ResourceID)
For Each Reso_As In Reso.Assignments
If Reso_As.TaskID = Job.ID Then
Reso_As.Text1 = Task_As.Text1
End If 'TaskID
Next Reso_As
Next Task_As
End If 'Nothing
Next Job

End Sub


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top