K
Keith Chadwick
I have been asked to set up the project schedule for an upcomming project and
I am running into some frustration.
Simply put I have a task that will take 8 hours between 2 resources, so 50%
allocated to each. But the task will be completed over a week. How do I
show this is one task. Do I use the Lag feature? Or sub tasks one for each
developer?
I have searched through the help and this basic information is not provided.
Any help would be appreciated.
Cheers
Keith
I am running into some frustration.
Simply put I have a task that will take 8 hours between 2 resources, so 50%
allocated to each. But the task will be completed over a week. How do I
show this is one task. Do I use the Lag feature? Or sub tasks one for each
developer?
I have searched through the help and this basic information is not provided.
Any help would be appreciated.
Cheers
Keith