Generic schedules

K

KimC

Is it possible to create a schedule that can start on Day 1 and finish on Day
500, without having a specific start date?
 
J

JulieS

Hi KimC,

No, I'm afraid that projects all are tied to a start date. However, you can
change the display of the timescale to show Day 1, Day 2 etc. Go to Tools >
Options, View tab. Open the Date Format choices to see what options there
are as far as date format.

If you are creating a template for re-use in other projects, you simply
change the start date of the project through Project > Project Information.

I hope this helps. Let us know how you get along.

Julie
 
J

Jan De Messemaeker

Also, through Format, Timescale, you can show D1.... D50 as a timescale
label.
HTH
 