J
jjoycepmp
I have a Master Schedule that links 20 other subschedules to it. I have
noticed within the Master Schedule that there are tasks that appear gray in
color and can not be munipulated, but can be deleted. Some appear to have
references back to the subschedules others do not. Can anyone explain to me
what these are and whether or not I should delete them?
noticed within the Master Schedule that there are tasks that appear gray in
color and can not be munipulated, but can be deleted. Some appear to have
references back to the subschedules others do not. Can anyone explain to me
what these are and whether or not I should delete them?