L
Logistics for Newday
Hi,
I wrote a project for an event in Aug 2007 which has about 1000 task lines
in it. I wish to use the same project that I wrote last year for this year's
event which takes place on exactly the same dates. Is there any way to
autocorrect/change the year in the Start and Finish columns without having to
go through the tasks line by line.
Grateful for any suggestions!
Thanks
I wrote a project for an event in Aug 2007 which has about 1000 task lines
in it. I wish to use the same project that I wrote last year for this year's
event which takes place on exactly the same dates. Is there any way to
autocorrect/change the year in the Start and Finish columns without having to
go through the tasks line by line.
Grateful for any suggestions!
Thanks