Grouping format

R

RWSkaggs

When I have tasks indented to create summary tasks. They lose their place in
the schedule (All summary tasks dispaly at the top of a group) when I use
grouping to organize my schedule. How do I get the summary tasks to stay with
their perspective subtasks?
 
J

Jim Aksel

When you do the grouping, look at the lower left corner of the window that is
open. There is usually a check box that tells MS Project to respect your
structure. See if that helps.
 