A
a.Phoenicis
I'm sorry to pose such a basic question, but I'm still learning both PM
and MP. I've searched the groups, but I can't find an answer to this...
perhaps I don't know how to phrase the question.
I have filled in my tasks & resources, and have set up the dependencies
and have a rudimentary schedule. I now need to tweak it for some
real-world constraints:
I have two similar specialized construction tasks that will occurr in
two different rooms but be done by the same sub-contractor. The tasks'
schedules are dependent upon the other tasks occuring in each room. The
two rooms are not dependent upon each other in any other respect.
Project wants to schedule the two tasks two weeks apart. I need to have
the sub-contractors come out only one time, even if that means that
other tasks are waiting.
I can force the issue by setting constraints on either end of those two
tasks to force them together, but I want to minimize the impact on the
overall project... is there a way to tell Project that these tasks must
occur consecutively? Please help!
and MP. I've searched the groups, but I can't find an answer to this...
perhaps I don't know how to phrase the question.
I have filled in my tasks & resources, and have set up the dependencies
and have a rudimentary schedule. I now need to tweak it for some
real-world constraints:
I have two similar specialized construction tasks that will occurr in
two different rooms but be done by the same sub-contractor. The tasks'
schedules are dependent upon the other tasks occuring in each room. The
two rooms are not dependent upon each other in any other respect.
Project wants to schedule the two tasks two weeks apart. I need to have
the sub-contractors come out only one time, even if that means that
other tasks are waiting.
I can force the issue by setting constraints on either end of those two
tasks to force them together, but I want to minimize the impact on the
overall project... is there a way to tell Project that these tasks must
occur consecutively? Please help!