Having problems with externally linked milestones

E

Elle

Hello,

They are linked FS there is no constraint on Milestone 1 in first plan but
it is showing as a different date from the milestone in the second plan

what are the reason this could be happening?

Ta
 
J

JulieS

Hi Elle,

You don't give us much information to work with.

Are the milestones linked F to S or are both milestones linked to a
common predecessor?
Does either milestone have an additional predecessor?
Is there lag or lead added to the link between milestone?
Are both tasks truly milestones - duration zero?

You can see your projects, we can't. So letting us know more details
would really help us help you.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
E

Elle

I think i've sorted the problem but can you just confirm that when i change a
milestone to 100% complete in one plan the same miletone in the other plan
won't automatically update?? and needs to be manually updated to 100%??
 