Chaps,
I am stuck on site with no P6 but I have MSP. I have four major milestones
with approximatley 50 activities attached to each but they are all over the
network (By system) I need to list the milestone with all the predessesor
activities listed underneth preferably in early finish order so that I can
see the critical activities which are pushing the milestone(s) out. I can
then trace back through the worst few to make sure the logic is correct. I
realise I can go through and code each activity with a code in a text field
but is there an easier/ better way?
Regards
SteveD
I am stuck on site with no P6 but I have MSP. I have four major milestones
with approximatley 50 activities attached to each but they are all over the
network (By system) I need to list the milestone with all the predessesor
activities listed underneth preferably in early finish order so that I can
see the critical activities which are pushing the milestone(s) out. I can
then trace back through the worst few to make sure the logic is correct. I
realise I can go through and code each activity with a code in a text field
but is there an easier/ better way?