Having problems with resource allocation

T

theonehunter

Need some help with resource allocation. I am trying to add resources to an
already existing project, but, everytime I add the reources, percentages pop
up and skew my hours... what am I doing wrong??
 
A

Al

If I understand you correctly, you have a task that is (say) 2 days in
duration. If you then add a resource and specify 50%, the duration of the
task changes to 4 days.

If this is you issue, then double click on the task, go to the advanced tab
and change the task type to "fixed duration".

Alternatively, change the default in MS Project.... Tools / Options /
Schedule / Default task type = fixed duration.

Regards
Alex
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top