How I can filter linked tasks in gantt chart (with bar type view) and see the
links between them.for example a task bar with tasks just after that.
 
J

JulieS

Hi toofan,

There is a combination view that I *think* will give you what you are
looking for.

Split your screen (Window > Split) to create the combination view.
Click your mouse in the bottom pane to activate the pane, and then choose
View > More Views to display the More Views dialog box.

Select the Relationship Diagram view.

When you select a task in the upper pane (Gantt chart) it will show you the
selected task's predecessors and successors in the lower pane (Relationship
Diagram).

I hope this helps. Let us know how you get along.
Julie
 
T

toofan

.....!!very nice tip..!!!but I cant work on change details like fs sf or
duration or dates in this view...!can I?Could you help for changing color of
task cells..too?
 
J

JulieS

Hi toofan,

You can't change the information *directly* in the Relationship Diagram view
in the bottom pane, but you can modify task link types (FS, SS etc.) in the
Task Form View. When you initially split from the Gantt Chart view, the
Task Form is the view in the bottom pane. Click in the bottom pane and
choose Format > Details, and you can display Predecessors and Successors in
the task form.

As far as changing the color of task cells, I'm afraid that is impossible.
Unlike Excel, there is no "fill" color to change the background of a task
cell. You can change text color, size, etc through Format > Font.

I hope this helps. Let us know how you get along.