L
LY
Hello!!
I am very new to ms project (just started using it last week!) and I am
scratching my head on some problems facing… I have listed down a few
questions that I am hoping to get help. I am currently using MS project 2000.
1) Each time I change a date in a task, date for some other task that are
not linked or related change as well. I have to keep readjust the dates for
every single task. What did I do incorrectly? How do I prevent it?
2) The project I am working on only consumes few hours for a day for each
task. For example
Task 1 - work 5 hour. It spreads out into different days in the time range
to be completed.
When I put down 100% complete, it will then change to show 40 hours work
day. Actually is t is only about 10 or less. How do I make it show the exact
hour I want and let the 100% complete line stays in Gantt Chart?
Also, when I enter the work hour in the Gantt chart view, (for example, 5
hours), the Gantt chart shrinks down to a small line! How do I make the bar
stretch across the bar?
3) How do I make the Gantt chart shows a task finish early than scheduled in
different color.. Or finish late as scheduled?
4) Is there a way to have a summary that shows task that need to pay
attention to or in alert stage?
Any tips / advise / solutions will be very appreciated!!!!!!!
L.Y
I am very new to ms project (just started using it last week!) and I am
scratching my head on some problems facing… I have listed down a few
questions that I am hoping to get help. I am currently using MS project 2000.
1) Each time I change a date in a task, date for some other task that are
not linked or related change as well. I have to keep readjust the dates for
every single task. What did I do incorrectly? How do I prevent it?
2) The project I am working on only consumes few hours for a day for each
task. For example
Task 1 - work 5 hour. It spreads out into different days in the time range
to be completed.
When I put down 100% complete, it will then change to show 40 hours work
day. Actually is t is only about 10 or less. How do I make it show the exact
hour I want and let the 100% complete line stays in Gantt Chart?
Also, when I enter the work hour in the Gantt chart view, (for example, 5
hours), the Gantt chart shrinks down to a small line! How do I make the bar
stretch across the bar?
3) How do I make the Gantt chart shows a task finish early than scheduled in
different color.. Or finish late as scheduled?
4) Is there a way to have a summary that shows task that need to pay
attention to or in alert stage?
Any tips / advise / solutions will be very appreciated!!!!!!!
L.Y