J
jeremy
Hi
I am sure there is something very simple here but I am unable to find
it.
In essence I have created a project with a number of start-finish
tasks and these are allocated to resources (people). I have allocated
(on the resource details window) 20% and 25% availability as these
guiys have to work on other things concurrently.
I didn't add any date constraints such as "must complete before" and
thought that MS project would simply extend the duration of tasks to
enable the required resources to work on them. But oh no - instead the
tool seems intent on overcommitting all the resources by 300 even
400%.
So I must be doing something fundamentally wrong - why won't project
just extend the duration of the tasks?
I entered my estimates for the work to be done in the "Work" column.
Should this actually be entered into the "Duration" column?
Appreciate any tips.
I am sure there is something very simple here but I am unable to find
it.
In essence I have created a project with a number of start-finish
tasks and these are allocated to resources (people). I have allocated
(on the resource details window) 20% and 25% availability as these
guiys have to work on other things concurrently.
I didn't add any date constraints such as "must complete before" and
thought that MS project would simply extend the duration of tasks to
enable the required resources to work on them. But oh no - instead the
tool seems intent on overcommitting all the resources by 300 even
400%.
So I must be doing something fundamentally wrong - why won't project
just extend the duration of the tasks?
I entered my estimates for the work to be done in the "Work" column.
Should this actually be entered into the "Duration" column?
Appreciate any tips.