D
dgmoore
I have a requirement to maintain a schedule (or, more accurately, a
calendar...) using MSProject. It is necessary that this Project file
maintain all dates as entered and not change data through
recalculation. It is also required that dependencies be displayed.
Basically, in this application, Project is used merely as a data
repository and Gantt chart generator. Although this is not how Project
is intended to be used, I have no other option in this instance.
I want to take advantage of such features as summaries, rolled up
progress, and the like that Project calculates automatically, so I
would like to use Start/Finish but ensure that those dates do not get
recalculated. To that end I have set calculation to manual, new tasks
start on current date, and tasks honor constraint dates = no.
Can anybody suggest anything else I need to allow for in this file?
Thanks
Dave
calendar...) using MSProject. It is necessary that this Project file
maintain all dates as entered and not change data through
recalculation. It is also required that dependencies be displayed.
Basically, in this application, Project is used merely as a data
repository and Gantt chart generator. Although this is not how Project
is intended to be used, I have no other option in this instance.
I want to take advantage of such features as summaries, rolled up
progress, and the like that Project calculates automatically, so I
would like to use Start/Finish but ensure that those dates do not get
recalculated. To that end I have set calculation to manual, new tasks
start on current date, and tasks honor constraint dates = no.
Can anybody suggest anything else I need to allow for in this file?
Thanks
Dave