Hide Weekends on Gantt Chart

R

Richard Wodabek

Is there a way to only display M-F on the Gantt chart and not the weekends?

Thanks

Richard.
 
J

Jim Aksel

No. Your best bet is to select a time scale where weekends are buried, such
as Months.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
I

infoseeker

Sir,
What you can do is on the timescaled portion of the Gantt Chart right click
and choose the Nonworking option and then under the formatting options you
can choose the do not draw option,hope this help.Also ensure that your
nonworking time is correctly defined
hope this helps
 
J

Jim Aksel

Good suggestion. However, the Gantt chart still shows all 7 days. Your
suggestion just avoids cololoring the column. This user wants to only show
work days.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 