I presume you're referring to start and finish dates.
Others may have a better approach but this certainly works.
1. Tools | Tracking | Save baseline ... | Save Iterim plan and choose
Save Start/Finish in Start1/Finish1.
2. Insert column Flag1, rightmousebutton on the column header and click
on Customize...
3. Click on the formula button and enter the line below:
([Start]=[Start1]) And ([Finish]=[Finish1])
4. Click on OK (to exit the formula entry) and then click on the radio
button labelled "use formula" (immediately below the Formula button and
click on OK.
5. Set the AutoFilter to ON.
6. Make your changes.
7. At any point while you are making your changes, simply click on the
autofilter triangle at the top of the Flag1 column and select No. This
will display all those tasks that have been changed.
If you do this sort of thing regularly, record the keystrokes in a macro,
attach the macro to a button and with a single-click you'll be ready to
start.
If I make a change in the Gantt, is there a way to
highlight what the resulting impact this change caused?
My plans are quite intricate and large, and so if I make a
change to a task in the Work column for instance, ideally
I'd like to see highlighted the resulting changes in other
tasks.
Thank you.
--