Dennis said:
How can I have Project automatically highlight (change
font) a task that is passed due? Maybe make it a
different color etc...
Create a filter (project menu/filter for.../more filters/edit
with the criteria
finish is less than ? (this will prompt for the date you want to use)
and
% Complete is less than 100%
Make sure that the "Highlight Filter" box is checked.
You can format the way the highlighted tasks show up by going to the Format
menu/text styles and formatting the highlight.
--