I use MSP as a planning tool. I do not use the scheduling engine. I set the
tasks type to "fixed duration" and unmark effort driven. In this way however
MSP does not tell that I assign resources to a task on days the resource
calendar shows as unavailable (non working).
Is there nevertheless an elegant way to avoid assigning resources to a fixed
duration task by taking into account their non working time or do I have to
check their calendar every time I assign them?