A
Andrew Barker
Help needed.
I have successfully created my project plan but have noticed that some of
the tasks are schedueld for the 25th, 26th of December and 1st of January. I
obviously wish to make these holidays and have done so by creating my own
calender making these non working days and uploading the info via project
information. Unfortunatly the changes do not seem to appear within the plan,
the task still shows work during these periods. Therefore my question is this
do I have to create my calender at the start of a project before any tasks
are entered or is project supposed to amend the working times according to
the non wokring times when a project calender is created be this at the
start, middle or end ? I have for the moment created a work around by
splitting the task into two and entering the appropriate start and end dates
so as to avoid work during these periods?
Any help gratfully receieved.
I have successfully created my project plan but have noticed that some of
the tasks are schedueld for the 25th, 26th of December and 1st of January. I
obviously wish to make these holidays and have done so by creating my own
calender making these non working days and uploading the info via project
information. Unfortunatly the changes do not seem to appear within the plan,
the task still shows work during these periods. Therefore my question is this
do I have to create my calender at the start of a project before any tasks
are entered or is project supposed to amend the working times according to
the non wokring times when a project calender is created be this at the
start, middle or end ? I have for the moment created a work around by
splitting the task into two and entering the appropriate start and end dates
so as to avoid work during these periods?
Any help gratfully receieved.