I have a large master project with lots of sub-projects. I want to be able to
mirror certain summary tasks, so I can show them at the top of the Project
with their dependencies only and w/o all the detail. Any ideas??
 
J

John

Brandyman said:
I have a large master project with lots of sub-projects. I want to be able to
mirror certain summary tasks, so I can show them at the top of the Project
with their dependencies only and w/o all the detail. Any ideas??

Brandyman,
Since you can't adequately show all the interactive dependencies on a
Summary Line, why not pick out the most important relevant milestones
and then mirror those in a section at the top of the master file. Then
all you need is a simple predecessor on the mirrored items. That will
give a much more informative picture than a Summary Line.

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top