How can I change the time scale?

A

Adam

I changed my timescale to show as day 1,2,3,...etc., I grouped in 10 day
intervals, which works fine, but the lable on the time scale starts showing
as 3, 13, 23, 33, etc.

My project starts on the 1st day and I want it to lable as 1, 10, 20, 30,
etc. How Can I fix that???
 
J

John

Adam said:
I changed my timescale to show as day 1,2,3,...etc., I grouped in 10 day
intervals, which works fine, but the lable on the time scale starts showing
as 3, 13, 23, 33, etc.

My project starts on the 1st day and I want it to lable as 1, 10, 20, 30,
etc. How Can I fix that???

Adam,
I assume by "grouped in 10 day intervals" you mean the timescale "count"
setting is "10".

My guess is that Tools/Options/Calendar tab is set for a week start of
Tuesday. Change the "week starts on" to Sunady and it should give what
you want.

John
Project MVP
 