P
Patrick Allmond
I know what I want to do with the resources but I cannot get MS Project to
do the math correctly.
I have a resource. Since people are not productive 100% of the time I need
that resource to be at around 70-75% effective in MS Project. In truth they
will be on the job 8 hours a day. But for productivity calculcation I'd like
them to be less that 100%. The resource will not be working on anything
else.
At the same time the resource costs me a price per hour for an 8 hour day.
I'd like that to be figured out properly also. If the person charges me
$1/hour to work, I'd like to see that every day s/he is on the project costs
me $1. At the same time I need to see that an 8 hour task will actually take
more than one day, and cost me over $8.
I tried changing the % utilized on the resource but the cost does not get
figured out correctly. If I change it to 70% and schedule an hour task, the
project only shows that it costs me $0.70 . In reality that tasks costs me
more than a $1.
Thank you
Patrick
do the math correctly.
I have a resource. Since people are not productive 100% of the time I need
that resource to be at around 70-75% effective in MS Project. In truth they
will be on the job 8 hours a day. But for productivity calculcation I'd like
them to be less that 100%. The resource will not be working on anything
else.
At the same time the resource costs me a price per hour for an 8 hour day.
I'd like that to be figured out properly also. If the person charges me
$1/hour to work, I'd like to see that every day s/he is on the project costs
me $1. At the same time I need to see that an 8 hour task will actually take
more than one day, and cost me over $8.
I tried changing the % utilized on the resource but the cost does not get
figured out correctly. If I change it to 70% and schedule an hour task, the
project only shows that it costs me $0.70 . In reality that tasks costs me
more than a $1.
Thank you
Patrick