I have a task that is utilizing 4 people, with a duration of 10 days, I add a
person in the middle of the task for only 2 days, how do I do it efficiently
and effectively
 
G

Gérard Ducouret

Hi Christloves,

Use the Task Form : Window / Split... and display the Schedule format:
Format / Details / Schedule
There you will find the Delay and the Work fields which will allow you to do
what you want for each resource.
You can also do that in the Task Usage view.
Hope this helps,

Gérard Ducouret
 
M

Manmeet Chaudhari

Hi
Add the resource as usual
Now to define exactly on which days he is working, go to Resource Usage view
and edit the table on the right side

Btw it will be a good idea to split the task into sub tasks and then assign
resources
Assigning 5 resources will cause confusion while tracking and monitoring the
progress
 