how do I ask for all work that needs to be worked on in the next .

J

Jim Aksel

Filter on Date Range.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
T

Tom

It only lets me pick a date as is from 01/01/08 to 02/01/08
What I want is the set the filter one time, to say "today" plus 10 days
so I don't have to pick a date range each time I use the filter.
 
J

JulieS

Hello Tom,

You could use a spare date field and customize the field with a formula:

ProjDateAdd(Now(),10*480)

That will show the date 10 days (assuming you use an 8 hour day) from
the current date. Then create a custom filter (perhaps based upon the
existing Date range filter) and reference the custom date field in the
filter.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 