Hello Tom,
You could use a spare date field and customize the field with a formula:
ProjDateAdd(Now(),10*480)
That will show the date 10 days (assuming you use an 8 hour day) from
the current date. Then create a custom filter (perhaps based upon the
existing Date range filter) and reference the custom date field in the
filter.
I hope this helps. Let us know how you get along.
Julie