How do I assign a unique task ID in Project which doesn't change

R

Roger-Eade

I'm looking for an automatic unique identifier for entries in the plan that
doesn't change as the task/activity moves in the plan. Both ID's & WBS's
change as the task moves.
 
J

JulieS

Hi Roger-Eade,

Insert the Unique ID field. The field is as you describe.

I hope this helps. Let us know how you get along.

Julie
 