How do I assign all tasks for a Resource A to Resource B

K

kamal

How do I assign all tasks for a Resource A to Resource B? Find and replace
all does not work :(

Cheers
 
J

JulieS

Hi Kamal,

Filter the project with the filter Using Resource..... and select
Resource A. This will show tasks assigned to Resource A. Select all
tasks that are shown after the filter is applied.

Click the Assign Resources button on the Standard toolbar. In the
Assign Resources dialog box, select Resource A. Click the Replace
button. In the Replace Resource dialog box, select Resource B. Click OK
to assign Resource B and close the Replace Resources dialog box. Click
the Close button to close the Assign Resources dialog box.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 