HOW DO I ASSIGN MANHOURS TO A TASK IN PROJECT?

L

ll2c00l

I want to do manning projections using MS Project and I need to be able to
assign manhours to each task. How do I do this?
 
D

Dale Howard [MVP]

ll2c001 --

Assuming you have added resources in the Resource Sheet view of your
project, apply the Gantt Chart view and then click Window - Split to apply
the Task Entry view. Select a task in the upper pane (Gantt Chart), then
select a resource in the lower pane (Task Form), and enter Units and Work
for that resource. Click the OK button to complete the assignment. Click
the Next button to advance to the next task in the project and continue the
process. Hope this helps.
 
M

Mike Glen

Hi ll2c00l ,

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #5 on resources, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

wrote:
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top