DanS
I'm trying to assign manhours by task not duration. Example if a one task
takes 100 manhours and/or 3 days because I place 4 men on the task, the next
task may take 100 manhours and/or 5 days because I place 2 men on the task.
I don't want the manhours to be the driving factor for the duration. Then, I
would like to run a report that could tell me based on the number of manhours
I asked for per task how many manhours there will need to be spent per week
of the project, telling me how many men I will require on the project to
complete this work throught the project.
takes 100 manhours and/or 3 days because I place 4 men on the task, the next
task may take 100 manhours and/or 5 days because I place 2 men on the task.
I don't want the manhours to be the driving factor for the duration. Then, I
would like to run a report that could tell me based on the number of manhours
I asked for per task how many manhours there will need to be spent per week
of the project, telling me how many men I will require on the project to
complete this work throught the project.