How do I assign Team/People Responsibilities to Individual Tasks

S

Somerled HK

I simply want to allocated either people or teams to an activity without
affecting the resource levelling. I need only to be able to extract or
identify the tasks to be carried out by each individual team.
 
J

Jan De Messemaeker

Hi,

If you want resources not to influence leveling, the simplest way is to give
these resources a very high availability (like 5000% or so)
HTH
 
S

Somerled HK

Jan,

Thanks, I had tried a large percentage for the resource but only up to 500%
so I'll try the "fixed task duration" method first and if that fails then
I'll try your 5000% resources.

Thanks - IAN
 
B

Brian K - Project MVP

Somerled said:
Jan,

Thanks, I had tried a large percentage for the resource but only up
to 500% so I'll try the "fixed task duration" method first and if
that fails then I'll try your 5000% resources.

Thanks - IAN

Well how many people are on Team X? 5000% would be fine if there were
50 people on the team. 500% would be appropriate if there were 5 people
on the team. "Not effecting leveling" is only good up to a certain
point. If you changed it to 5000 and the team only had 5 people then
for sure leveling would not be 'effected' but it would also be
meaningless. Project would allow you to assign 50 man-days to that team
on any given working day! Up the Max Units of these 'generic' resources
only to the level that they represent the team size.

I wrote an article about doing this exact thing back in 2001.
http://techrepublic.com.com/5100-6315_11-1028236.html#
 
W

whiteair

What you can do is use the resource "usage view" along with some grouping and
you have what you are looking for!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top