T
Tracey S
I have entered a task and have a bar on my gantt chart, I have a deadline
arrow further along the same task line and I need to draw a line (in green)
to connect the two together. I can do this OK, but when the project is
printed the lines are not in the correct place.
I have tried drawing and attach to task with right hand attachment point but
the line does not appear in the correct place and when I try to move it, it
also prints in the wrong place.
Any ideas would be very much appreciated.
arrow further along the same task line and I need to draw a line (in green)
to connect the two together. I can do this OK, but when the project is
printed the lines are not in the correct place.
I have tried drawing and attach to task with right hand attachment point but
the line does not appear in the correct place and when I try to move it, it
also prints in the wrong place.
Any ideas would be very much appreciated.