How do I build a report that shows a track's summary task's due da

P

pfarsad

Hi!
I want to build a report that shows all of my summary tasks and the due
dates. For example I have three summary tasks (concepts, R&D, and creative
handoff) I want a report that would show be able to summarize the dates those
summary tasks need to be done in my project track.
 
M

Mark Dietrich

Project/Filtered For/Summary Tasks

If that does not give you what you want another option to consider is
placing "milestone" at those critical points. This allows you to filter
based on "milestones".
 
P

pfarsad

Hi Mark,

So I tried what you suggested and I am still stuck. I need to customize it
so that its in a report that I could pass out to the team. My dream set up
would be to have a table with all the summary tasks on it and MS Project
actually pulling the dates from the different projects. Is this possible?
 