K
Kevin
Hi,
i have set up 3 recurring tasks in Project 2000:
1 Daily production
2 Daily request review
3 Weekly production (only on Mondays)
I need them to be linked dependent (FS) on each other but can 't find out
how to do this (asked people with experience and searched the internet). When
i try to link them 2 starts after 1 has finished all of its recurring tasks
i.e. in 2009. I need task one to start then task 2 every day and then on
Mondays task 3 after both of these have finished.
any help would be appreciated
thanks
best regards
kevin
i have set up 3 recurring tasks in Project 2000:
1 Daily production
2 Daily request review
3 Weekly production (only on Mondays)
I need them to be linked dependent (FS) on each other but can 't find out
how to do this (asked people with experience and searched the internet). When
i try to link them 2 starts after 1 has finished all of its recurring tasks
i.e. in 2009. I need task one to start then task 2 every day and then on
Mondays task 3 after both of these have finished.
any help would be appreciated
thanks
best regards
kevin