Unfortuntely, a constraint type is not what the poster asked for :-((
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
I am trying to change the predecessor default from finish to start to
start
to start.
You would have to change it on the task information. There is no
option to change the default for the constraint type you will need to
change on each task. The good news is you can change all of your
tasks at once by highlighting the tasks you want to change and then
open the task information dialog and click on the advance tab. You
can then change the constraint type for those highlighted tasks.