How do i generate a trend graph for percentage complete

D

Don Barrett

I was looking for a trend graph that has dates along the X axis so we could
see the progress of each team for each day. This graph would plot future
dates as well showing % that should be complete on each future day..
 
W

William Raymond [MVP]

Hi Don,

The "Analyze Timescaled Data in Excel" feature ought to give this to you.

1) Run MS Project and go to "View->Toolbars->Analysis".
2) A new toolbar will display in MS Project. Click on the "Analyze
Timescaled Data in Excel" button and follow steps in the wizard.

-Bill
 