How do I get project costs for 8.5 hours / day working time?

B

Bala

'am trying to build a project plan with 8.5 hours of work time per day. I
have shcnges the working time in the calendar. When I roll up costs, it only
takes 8 hours/ day. Please advise how I can get project budget with 8.5 hours?
 
J

Jim Aksel

You were almost there....
Tools/Change Working time...
Make adjustments there.
Then click the Options... button, pull the Calendar Tab
Hours per Day 8.5
Hours per week: 42.5
days per Month 20 (or 22 if you like)
 
M

Mike Glen

Hi Bala,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top