I have two resources working on independent tasks which both start at the
same time. Task one will end approximately 14 weeks prior to task two - at
which point my second resource will roll over to the first task to help
complete the task and reduce the duration. When I add the second resource to
the first task - it reduced the duration of the entire task by half - when in
reality - only the duration of the remaining weeks, when both individuals are
working together, should impact the duration of the entire task. How do I get
Project to calculate this correctly?
same time. Task one will end approximately 14 weeks prior to task two - at
which point my second resource will roll over to the first task to help
complete the task and reduce the duration. When I add the second resource to
the first task - it reduced the duration of the entire task by half - when in
reality - only the duration of the remaining weeks, when both individuals are
working together, should impact the duration of the entire task. How do I get
Project to calculate this correctly?