D
Diane
Some of our resources have level of effort tasks in addition to their fixed
work type tasks. We would like to actively show those level of effort tasks
in the schedule, instead of just decreasing that resources total available
units. For example, Jane has one level of effort task, estimated to take 20%
of her time on average throughout the year. She also performs fixed work
tasks. I believe the only way for me to show the level of effort tasks is to
treat them as a reoccuring task, reoccuring say on a weekly basis for 8 hrs
per week (20%). Is there another way to do this?
Thanks!
work type tasks. We would like to actively show those level of effort tasks
in the schedule, instead of just decreasing that resources total available
units. For example, Jane has one level of effort task, estimated to take 20%
of her time on average throughout the year. She also performs fixed work
tasks. I believe the only way for me to show the level of effort tasks is to
treat them as a reoccuring task, reoccuring say on a weekly basis for 8 hrs
per week (20%). Is there another way to do this?
Thanks!