How do I include Resource Names in the text bars of a calendar rep

M

MK

Default text shown in a Calendar view appear to be task name and duration. I
want to show task name and resources assigned to the task. Can I choose
which text is displayed in the text bars of a calendar view?
 
J

JulieS

Hi MK,

In the calendar view, choose Format > Bar Styles. Select Critical tasks and
in the Task Type list. Change the Text section towards to bottom to read
"Name, Resource Names" (no quotes around the text.)

I hope this helps. Let us know how you get along.

Julie
 