Thank you for the reply Wiley.
There are tasks in front that are constraining the problem task. The
predecessors are there because they need to be done first.
I can manually move the task to the next day but that kind of defeats the
purpose of having a scheduling program. I guess this would be no big deal if
there was just one case where this was a problem but I'm working on dozens of
short tasks (they are coordinating phone calls) each of which must be done in
specific time of day windows without spanning days. They each have
predecessors, successors, limited calendars and priorities to get them into
the right spot during the day and in the best sequence. Just to make things
more complicated, this is a 3 week long trip on-site to 1/2 a dozen locations
across the country and each have multiple groups of interrelated and multiple
unrelated tasks, many with different restricted working hours on 6 different
work calendars. Moving just one task impacts at least several others and
could ripple through to the end of the trip. Because of possible external
conflicts, I'm also creating 4 different work plans to allow others to select
the one with the least impact on them. Before getting Project, I tried to do
the whole thing manually in a spreadsheet and discovered just how much work
it is to optimize the schedule.
Is there a setting that I can set on a task will keep that task from being
split across days and auomatically move it to another day if it can't be done
on the current day without manually constraining it to a specific start
time/date?
Thanks
Brian