Hi Craig,
Welcome to this Microsoft Project newsgroup
I would advise against scheduelling from the finish, as every task will
finish as late as possible and thus everything becomes critical and you lose
any flexibility that Project could give you. Schedule from the start and
create a deadline task based on the latest date the job can finish. When
you level, you will then see the amount of time you have to play with. If
it's going to be late on the deadline, at least you will be aware of it and
do something (like overtime) to bring forward the finish to within the
deadline. Let Project do the scheduelling to see what's possible with your
inputs. You can then adjust to meet your target.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP